Construction Updates for New Development

Posted on: November 1, 2019

Broadstone Update 11/1

Over the course of the next month, in terms of site work, the Thrasher Street final sidewalks will be completed and the internal roads will be installed.  Site retaining wall installation will also be completed while the site park pergola structure framing begins.

At the renovated buildings, interior finishes (such as cabinets, counter tops, tile, paint) are being installed.  At the new buildings, wood framing will continue around the new parking garage with window installation to follow right behind.