Construction Updates & Variances

Sign up for text/email alerts here! Look under the "News Flash" category.
  1. Library Update 8/6/20 - Early Morning Concrete Pour on 8/12

    Cooper & Co. and our Gwinnett Construction Project Manager have informed us that there will be an early concrete pour next Wednesday 8/12 starting at 1 a.m. at the library development at Lillian Webb Park. They are working to pour 600 yds, which will Read on...
  2. Norcross Greenway Project: Request for Feedback & Comments

    In keeping with Governor Brian Kemp’s directive to keep state government agencies functioning as Georgia combats the COVID-19 pandemic, Georgia DOT is moving forward by placing project information for review and feedback into an internet platform to compl Read on...
  3. N. Peachtree Sidewalk Update 7/31/20

    On Tuesday 7/21, the City was notified that the intended location for the fire hydrant location could not be achieved due to more rock. Read on...
  4. N. Peachtree Sidewalk Update 7/21/20

    The water line team is on site today 7/21 relocating a fire hydrant. The grading/drainage team will be back on Thursday 7/23 to resume storm drainage and curb/gutter construction on the southern half of the project. Relocation of the other fire hydrant Read on...
  5. N. Peachtree Sidewalk Update 7/14/20

    Our City Engineer held a short conference call/webinar with residents at 12-noon today to give a high-level update on the project and answer questions. The city was informed this morning by Gwinnett DWR and the contractor that they have pushed the planned Read on...
  6. N. Peachtree Sidewalk Update 7/2/20

    Work has been humming along for the last few weeks after a slowdown in May/early June due to the presence of rock and some administrative issues between Gwinnett County and the water line contractor. Those have been resolved and the water line work... Read on...
  7. Library Update 7/2/20

    Progress continues on pouring concrete columns. Lately, the construction team has been working through an issue related to concrete strength. Materials testing indicated that some concrete was used in the columns, and unfortunately did not meet design... Read on...
  8. Library Update 2/3/2020

    The contractors for the new Norcross Library at Lillian Webb Park will be closing Britt Avenue on February 3, 2020 to start mobilization. Read on...